Completion Date:
April 2023
Duration:
36 Months
CHALLENGE – Project was delayed due to COVID.
SOLUTIONS – We employed an agile approach to resourced allocation in line with the project needs. This ensured our business was able to navigate the financial challenges whilst delivering the required service to the client .
KYALAMI CORNER
RECONFIGURATION
Completion Date:
April 2021
Duration:
7 Months
CHALLENGE – We worked with a brand new team on a very tight programme .
SOLUTIONS – We aligned our goals to that of the rest of the contractor and held regular status meetings to ensure on time and budget delivery.
KINGSLEY
SHOPPING CENTRE
Completion Date:
October 2021
Duration:
26 Months
This project saw us refurbishing an existing shopping center in Pretoria CBD to modernise and upgrade.
HAZELDEAN CENTRE
DISCHEM UPGRADE
Completion Date:
July 2021
Duration:
3 Months
The scope of this project was to increase of the current Dischem store’s footprint, upgrade the store interiors and also included the installation of new HVAC system.
PICK N PAY ON NICOL
FLAGSHIP STORE
Completion Date:
April 2020
Duration:
9 Months
CHALLENGE – Keeping the store fully operational throughout the construction period .
SOLUTIONS – By ensuring our teams where on site at all times to supervise housekeeping and sequenced disruptive work during off peak hours to minimise disruption.
CRESTA AQUARIUM
INSTALLATION PROJECT
Completion Date:
September 2018
Duration:
18 Months
CHALLENGE – Specialised bespoke installation , 1st of its kind in Africa.
SOLUTIONS – We extensively researched the risks involved and had an intense risk mitigation procedure. We imported specialists from Italy for certain task execution. Our communication skills helped us bridge the knowledge, industry regulation and multinational team coordination.