the results speak for themselves From the ground up or in the live environment,

GA RANKUWA CITY

TENANT COORDINATION

Completion Date:

April 2023

Duration:

36 Months

CHALLENGE – Project was delayed due to COVID.

SOLUTIONS – We employed an agile approach to resourced allocation in line with the project needs. This ensured our business was able to navigate the financial challenges whilst delivering the required service to the client .

KYALAMI CORNER

RECONFIGURATION

Completion Date:

April 2021

Duration:

7 Months

CHALLENGE – We worked with a brand new team on a very tight programme .

SOLUTIONS – We aligned our goals to that of the rest of the contractor and held regular status meetings to ensure on time and budget delivery.

KINGSLEY

SHOPPING CENTRE

Completion Date:

October 2021

Duration:

26 Months

This project saw us refurbishing an existing shopping center in Pretoria CBD to modernise and upgrade.

HAZELDEAN CENTRE

DISCHEM UPGRADE

Completion Date:

July 2021

Duration:

3 Months

The scope of this project was to increase of the current Dischem store’s footprint, upgrade the store interiors and also included the  installation of new HVAC system.

PICK N PAY ON NICOL

FLAGSHIP STORE

Completion Date:

April 2020

Duration:

9 Months

CHALLENGE – Keeping the store fully operational throughout the construction period .

SOLUTIONS – By ensuring our teams where on site at all times to supervise housekeeping and sequenced disruptive work during off peak hours to minimise disruption.

CRESTA AQUARIUM

INSTALLATION PROJECT

Completion Date:

September 2018

Duration:

18 Months

CHALLENGE – Specialised bespoke installation , 1st of its kind in Africa.

SOLUTIONS – We extensively researched the risks involved and had an intense risk mitigation procedure. We imported specialists from Italy for certain task execution. Our communication skills helped us bridge the knowledge, industry regulation and multinational team coordination.